Chapter 13 - Wage Determination - Problems - Page 285: 4a

Answer

$\$1,000$ (per month / per worker).

Work Step by Step

1 worker clears 1 acre/month → revenue = $\$1,000$/acre. Equipment rental cost to employer = $\$150$ per worker per month. Work time = $40$ hours/week × $4$ weeks $= 160$ hours/month. Marginal revenue product (MRP) of one worker for one month MRP = value of the extra output produced = $\$1,000$ (per month / per worker).